Subject: B600 Installation Schedule Status
Date: Sun, 11 Apr 1999 10:50:13 -0500
From: "Zappia, Tim" <Tim.Zappia@mts.com>
To: Brad Thoen <Brad.Thoen@mts.com>, Craig Campbell
     <Craig.L.Campbell@mts.com>, Grant Ovsak <Grant.Ovsak@mts.com>,
     Kevin Laffen <kevin.Laffen@mts.com>, Mike Nemeth <Mike.Nemeth@mts.com>,
     Paul Randall <Paul.Randall@mts.com>, Rod Larson <Rod.Larson@mts.com>,
     Tom Miller <Tom.Miller@mts.com>
CC: "Gustafson, Neal" <Neal.Gustafson@mts.com>

Hello Everyone,

Our plans have changed.  There will almost certainly be a delay in
filling the basin with water.  I should hear officially by the middle of
this week.  Rumor has it that the delay could be from 2 weeks to a
month.  The problem is that the people building the wave absorber are
behind schedule.  This is actually good news for us.  The site is still
pretty dirty and any delay is to our benefit.  The longer we wait the
less dirt and grime the system, and us too, will be exposed to and the
less risk we have of damaging something.

So, we will reshedule for sometime in May.  I apologize for any
inconvenience this causes you and would like to know if there are any
scheduling conflicts with other projects that we need to work around.

By the end of this week all the miscellaneous mechanical equipment
should be installed, the hoses hooked up and ready for flushing (maybe
even do the flushing), and the cable trays and all power will be hooked
up.  The next time out Tom Miller and Paul Randall will come first to
connect the cables and get the computers and electronics working.  Then
the rest of the team will come and we'll bring the system to life.

Hugs and Kisses,

Tim