Subject: Re: Questions-Dalian
Date: Fri, 20 Aug 1999 08:54:00 +0800
From: Joe Ma <joema@bj.col.com.cn>
Organization: MTS ( China)
To: "Rood, Omar" <Omar.Rood@mts.com>
CC: "Ma, Joe" <joe.ma@mts.com>, "Smith, Jim" <Jim.Smith@mts.com>,
     "Larson, Rod" <Rod.Larson@mts.com>,
     "Petersen, Don" <Don.Petersen@mts.com>

Thanks, Omar.

I will transfer your reply to Mr. Zhu ASAP.

About the installation time, I believe Dalian people will fully
understand the reason for delay is not MTS.  They will appreciate your
efforts on this job.

Regards,
Joe

Rood, Omar wrote:
>
> Hello Joe,
>
> 1.  We will provide special blocks for mounting the accelerometers and they
> can not be mounted until we are on site.
>
> 2.  I did not notice the oil pit when I was at Dalian.  Space is a big
> problem under the table, I think it best if the pit is covered but I will
> ask Don Petersen, the designer, if another place will work.  (Don, please
> look at this question)
>
> 3.  We will ship as soon as they make their visit, we will then come install
> when the parts arrive Dalian. I expect to be done before the end of this
> year. We are not responsible for the delay of their visas so I hope they
> understand our plan was to do this installation earlier.
>
> Regards
> Omar
>
> > -----Original Message-----
> > From: Joe Ma [SMTP:joema@bj.col.com.cn]
> > Sent: Wednesday, August 18, 1999 2:31 AM
> > To:   Rood, Omar
> > Subject:      Questions
> >
> > Hi, Omar.
> >
> > Mr Zhu asked me two questions after he looked the drawings from you .
> >
> > 1) He wants to know where and how the accelerometer(s) should be put on
> > the table. He said MTS should suggest the position and it was not showed
> > on the drawing. After he got the position he will have somebody  do it.
> >
> > 2) He metioned that the area for the new HSM is a pit for gathering the
> > leaked oil before ( 400mm x 400mm). If we insist to put HSM there, then
> > he has to cover it with a steel plate.  Or you could put the HSM in
> > other place?
> >
> > Mr Zhu is now in Shenyang for the visa.  Mr. Kong called me and
> > expressed the worry about installation time, it should meet the schedule
> > of acceptance by the goverment by end of this year . He is going to
> > Taiwan from Aug 29 to Sep 12.So He wants to go to Mpls directly to do
> > the acceptance first, then the equipment can be shipped out as early as
> > possible.  Miss Wang will make arrangement in detail later.
> >
> > Regards,
> > Joe
> >