Subject: KIMM release change
Date: Tue, 2 Jan 2001 09:55:03 -0600
From: "Chua, David" <David.Chua@mts.com>
To: "Buskovick, Keith" <Keith.Buskovick@mts.com>
CC: "Rood, Omar" <Omar.Rood@mts.com>, "Larson, Rod" <Rod.Larson@mts.com>,
     "Chua, David" <David.Chua@mts.com>

Keith,

Sorry to start the year off like this but Omar just came and talked to
me about the release we made before shutdown.  He said that it would be
a better idea to split up the release into 3 parts.  The DUCs, the 3-stg
Valve drivers, and the rest of the items.  We need to do it this way
because the DUCs and the Valve drivers are going to hold the release up
for too long.  He plans on getting the DUCs and VD from another project
of his and use the parts that we release to replace them.

So, what we need to do is to change the release to reflect what is shown
above.  The DUCs and VD won't be available until June-July so go ahead
and put their C1 date as such.  June 15th or so.  For the rest of the
items, go ahead and put it a C1 date of 2/1 if that is being too
optimistic let me know and we can adjust as needed.

Let me know of any questions.

Thanks,
David

=====================================
David Chua
Design Engineer - Advanced Engineering Solutions Division
MTS Systems Corporation ( http://www.mts.com )
(952)974-6125
=====================================