Subject: RE: KIMM Service Engineer
Date: Thu, 5 Jul 2001 08:27:17 -0500
From: "Rood, Omar" <Omar.Rood@mts.com>
To: "Lee, SeogBong" <Seogbong.Lee@mts.com>
CC: "Ko, HeungLyul" <Heunglyul.Ko@mts.com>, "Chua, David"
     <David.Chua@mts.com>, "Larson, Rod" <Rod.Larson@mts.com>,
     "Nelson, Terry" <Terry.Nelson@mts.com>

Hello SeogBong,

My hope is the end of August but perhaps it will be sometime in the
first 2 weeks of September.  Changing controllers has many possible
problems so it depends how lucky we are.

Regards
Omar

>  -----Original Message-----
> From:         Lee, SeogBong
> Sent: Wednesday, July 04, 2001 8:20 PM
> To:   Rood, Omar
> Cc:   Ko, HeungLyul
> Subject:      RE: KIMM Service Engineer
>
> Hello Omar,
>
> When do you expect to complete this installation?
> Bests,
> Seogbong
>
>  -----Original Message-----
> From:         Rood, Omar
> Sent: Thursday, July 05, 2001 2:19 AM
> To:   Lee, SeogBong
> Subject:      RE: KIMM Service Engineer
>
> Hello Seogbong,
>
> If he arrives 13 August, since his English is good, that should be
> enough time for him to learn about the new controller.
>
> We will plan on him arriving on the 13th of August.
>
> Thanks
> Omar
>
>        -----Original Message-----
>       From:   Lee, SeogBong
>       Sent:   Wednesday, July 04, 2001 12:19 AM
>       To:     Rood, Omar
>       Cc:     Ko, HeungLyul; Chua, David; Larson, Rod; Nelson, Terry;
> Yoo, Yangseok
>       Subject:        RE: KIMM Service Engineer
>
>       Hello Omar,
>
>       I thinks he need some training for the first two weeks in our
> office.
>       I expect he is available from 13th of Aug.
>       Thanks,
>       Best regards,
>       Seogbong
>
>        -----Original Message-----
>       From:   Rood, Omar
>       Sent:   Wednesday, July 04, 2001 12:25 AM
>       To:     Lee, SeogBong
>       Cc:     Ko, HeungLyul; Chua, David; Larson, Rod; Nelson, Terry
>       Subject:        RE: KIMM Service Engineer
>
>       Hello Seogbong,
>
>       Attached is  our planned project schedule for installation.  It
> is the same as the one I sent HL earlier except the start has been
> delayed until 18 July.
>
>       About a FSE.  To be honest, we don't need a FSE for the
> installation.  But how will MTS-Korea do maintenance on the system if
> no one in MTS-Korea understands how to operate it?
>
>       Your new hire sounds like someone who would be a good choice to
> be the FSE for this project, when will he be available?
>
>       Regards
>       Omar
>
>                -----Original Message-----
>               From:   Lee, SeogBong
>               Sent:   Tuesday, July 03, 2001 1:39 AM
>               To:     Rood, Omar
>               Cc:     Ko, HeungLyul; Chua, David; Ruzicka, Larry
>               Subject:        RE: KIMM Service Engineer
>
>               Hello Omar,
>
>               How are you? I am so sorry we have no FSE available in
> this installation.
>               We have three FSE. One of them is on the international
> core training in Mpls.
>               Mr. Ko is installing the air bag and hard line of 4
> poster road simulator and MAST.
>               These projects are expected to be completed by about the
> second week of Aug.
>               Mr. Kwack have to support some percall services and the
> calibration of Kia K&C
>               and a few of MTD systems. We are very busy.
>
>               We will hire new FSE, he will join us next Month. He
> have worked for Daewoo motor company.
>               He was dispatched Daewoo Motor Poland Technical Center
> for two year, and move to Daewoo Motor Company Worthing Technical
> Center in UK.
>               He had worked for three year there, he was a electrical
> test engineer. He have a very good english skill.
>               If you need his support, we can do that.
>
>               First of all, please send your master plan, I will
> review and be looking for something to help you.
>               What is your opinion? Please let me know.
>               Best regards,
>               Seogbong
>
>
>                -----Original Message-----
>               From:   Ko, HeungLyul
>               Sent:   Tuesday, July 03, 2001 1:30 PM
>               To:     Lee, SeogBong
>               Subject:        FW: KIMM Service Engineer
>
>               Hi Seogbong,
>
>               Please check the service engineer schedule. KIMM
> installation will start from July 18 for almost month and half. I am
> not sure it is required MTS Korea service engineer to stay entire
> installation period. Please discuss with Omar and David for the
> detail.
>
>               Best regards,
>               HL
>
>                -----Original Message-----
>               From:   Rood, Omar
>               Sent:   Monday, July 02, 2001 11:36 PM
>               To:     Ko, HeungLyul
>               Cc:     Nelson, Terry; Larson, Rod; Chua, David
>               Subject:        RE: KIMM Service Engineer
>
>               Hello HL,
>
>               Will Mr. Kwanghun Ko be the MTS-Korea service person
> assigned to this installation?  Or, if someone else, please send us
> his name.
>
>               Thanks
>               Omar
>
>                        -----Original Message-----
>                       From:   Chua, David
>                       Sent:   Tuesday, June 26, 2001 1:05 PM
>                       To:     Rood, Omar
>                       Cc:     Nelson, Terry; Larson, Rod
>                       Subject:        KIMM Service Engineer
>
>                       Omar,
>
>                       Will a service engineer  be available during the
> KIMM Seismic Table Controller upgrade installation?  Mr. Kwanghun Ko
> was helping Dale and me during our previous trip.
>
>                       Thanks,
>                       David