Don,

My plan for this project was for acceptance this FY (US1. 18440.EQT).

See below, there has been a major building delay, originally May, then a
welcome slip until an estimated June 15 date, now it has slipped even
more until the end of September.

Therefore installation can't really start until next FY and the project
should be accepted by the end of the calendar year.

Omar

-----Original Message-----
From: Schwartzkopf, Steve
Sent: Thursday, January 31, 2002 12:44 PM
To: Rood, Omar
Subject: FW: Delivery date


-----Original Message-----
From: John Drumm [mailto:jdrumm@strongtie.com]
Sent: Thursday, January 31, 2002 12:43 PM
To: Sydeski, Ray; Lundbeck, Jeff; Schwartzkopf, Steve
Subject: Delivery date

Gentlemen,

Our contractor has notified us that the date for first crane use has
slipped to September.  They are saying that we would be able to take MTS
equipment delivery some time between September 3, and September 30.
Let's error on the safe side and say we would be able to unload
equipment on September 30.

Best regards,

John Drumm

Simpson Strong-Tie Co.

Tel:  209/245-3244

Fax: 209/245-3408

Voicemail: 800/925-5099 ext. 9141