Subject: FW:(Takenaka) Initial Adv Release, Merha Tibebu, US111641.EQT-21
Date: Mon, 2 Aug 1999 14:12:07 -0500
From: "Rood, Omar" <Omar.Rood@mts.com>
To: "Imafuku, Nobuhiro" <Nobuhiro.Imafuku@mts.com>
CC: "Katabami, Yoshihiro" <Yoshihiro.Katabami@mts.com>, "Nagai, Tetsu"
     <Tetsu.Nagai@mts.com>, "Larson, Rod" <Rod.Larson@mts.com>, "Tieman, Bob"
     <Bob.Tieman@mts.com>, "Tibebu, Merha" <Merha.Tibebu@mts.com>,
     "Harden, Chris" <Chris.Harden@mts.com>

Hello Fuku,
Big Problem
1.  Note,  the acuators are scheduled later than first promised.
Before the order, I was promised 4 1/2 to 5 months (mid October), now
the promise is November.  Also, since actuator manufacturing is
completing jobs 1 month later than promised (My last 3 jobs)- we will
probably get the actuators in December for checkout, late Dec for
shipping by Ocean, Therefore late January for delivery.
2. I had been promised and therefore quoted to MTS-Japan, 6 months to
shipping from date of order (i.e. ship by 8 December 1999 on the ocean)
3.  Given the delay, today I checked the contract.  Whoever wrote the
contract for Takenaka wrote delivery by October 31, 1999.  With contract
signed on 8 June 1999, that date was not the 6 months I had
promised??????????  With 6 weeks shipping time, a 31 October delivery
required being finished checkout at MTS by 15 September, therefore that
would have required design and manufacturing in 3 months time, CRAZY.

Omar

> -----Original Message-----
> From: Tibebu, Merha
> Sent: Monday, August 02, 1999 7:32 AM
> To:   Rood, Omar
> Subject:      FW: Initial Adv Release, Merha Tibebu, US111641.EQT-21
>
> Omar,
> This is the schedule I got from the Planner for Takanaka. I would like
> you to be aware of it ahead of time. If the date is not acceptable for
> you please let Chris know.
> Thanks,
> Merha
>
> -----Original Message-----
> From: Harden, Chris
> Sent: Thursday, July 29, 1999 12:43 PM
> To:   Tibebu, Merha
> Subject:      FW: Initial Adv Release, Merha Tibebu, US111641.EQT-21
>
> Merha,  c1 of 11/4 confirmed.  The forging has a ten week lead time,
> then Al Kremer needs 4 weeks to build the parts in his shop, and I
> need two weeks to assembly the actuator.
> Chris
>
> -----Original Message-----
> From: Earp, Gwenda
> Sent: Wednesday, July 28, 1999 3:41 PM
> To:   Harden, Chris
> Cc:   Tibebu, Merha
> Subject:      FW: Initial Adv Release, Merha Tibebu, US111641.EQT-21
>
> erc processed 7/28/99
>
> -----Original Message-----
> From: Super-User [SMTP:root@dodsun.mts.com]
> Sent: Wednesday, July 28, 1999 3:21 PM
> To:   gwenda.earp@mts.com
> Subject:      Initial Adv Release, Merha Tibebu, US111641.EQT-21
>
>
>    Use Courier font for best viewing
>    and printing of this form from a PC
>
> ====================================================
> Initial Advance Release  -- July 28, '99
> ====================================================
>
> Network Project No         Assembly    Qty Planner
> ------- ----------         --------    --- -------
> 905112  US111641.EQT-21    100-015-976  1  Chris Harden
>
>
> Requestor      : Merha Tibebu
> Initials       : M - T
> MailStop       : 127
> Phone Ext      : 4301
>
>
> Customer       : Takanaka
> Requested Cmpl : 10/7/99
> Actual Complete:
> Subjob Engr    : Merha Tibebu
> Project Engr   : Omar Rood
> ERC Intls/date :  [Earp, Gwenda]  erc processed 7/28/99